20 Oct · generated 20 Oct, 09:05 pm (cron)
Production report — 20 Oct
17/59 tasks complete (29%). 7 in progress, 35 not started, 0 blocked.
Today: 3 task(s) completed · replies from 6/6 people followed up.
⚠️ 3 overdue: Cutting plan & nesting (20T Double Girder EOT Crane, 50%) — Imran: drawing revision pending from design; Wheel turning & boring (20T Double Girder EOT Crane, 50%) — Mahesh: operator was on leave; Dimensional check (20T Double Girder EOT Crane, 50%) — Pooja: machine was down, maintenance came today
📝 Reasons given: Cutting plan & nesting — Suresh Yadav: material not received yet; Dimensional check — Suresh Yadav: machine was down, maintenance came today; Plate & section procurement — Suresh Yadav: final welding still pending; Cutting plan & nesting — Imran Khan: drawing revision pending from design; Dimensional check — Imran Khan: vendor promised supply by tomorrow; Wheel turning & boring — Mahesh Patil: operator was on leave
↔️ Answers differ (kept open): Plate & section procurement — Suresh Yadav: not done, Imran Khan: done
• Painting: 0/9 done, avg 0%
• Dispatch: 0/6 done, avg 0%
• Machining: 6/10 done, avg 65%, 1 overdue
• Fabrication: 6/21 done, avg 38%, 2 overdue
• Electrical: 5/13 done, avg 46%
Complete
17/59
Completed today
3
Overdue
3
Replies
6/6

By work

Painting0/9 · 0%
Dispatch0/6 · 0%
Machining6/10 · 65% · 1 overdue
Fabrication6/21 · 38% · 2 overdue
Electrical5/13 · 46%

Today's updates

  • Cutting plan & nesting (20T Double Girder EOT Crane) → 50% · Team
    Suresh: not done (material not received yet) · Imran: not done (drawing revision pending from design)
  • Dimensional check (20T Double Girder EOT Crane) → 50% · Team
    Suresh: not done (machine was down, maintenance came today) · Imran: not done (vendor promised supply by tomorrow) · Pooja: not done (machine was down, maintenance came today)
  • Plate & section procurement (10T Single Girder EOT Crane) → 67% · Team
    Kept open — answers differ (Suresh: not done (final welding still pending) · Imran: done)
  • Cutting plan & nesting (10T Single Girder EOT Crane) → 100% · Team
    Marked done — Suresh: done · Imran: done
  • Weld inspection (DPT/UT) (20T Double Girder EOT Crane) → 100% · Team
    Marked done — Suresh: done · Imran: done · Pooja: done
  • End carriage fabrication (10T Single Girder EOT Crane) → 25% · Team
    Suresh: in progress · Imran: in progress
  • Wheel turning & boring (20T Double Girder EOT Crane) → 50% · Mahesh Patil
    Mahesh: not done (operator was on leave)
  • Forged wheel blanks (10T Single Girder EOT Crane) → 100% · Mahesh Patil
    Marked done — Mahesh: done
  • Panel testing (20T Double Girder EOT Crane) → 67% · Vikram Singh
    Vikram: in progress
  • Switchgear & VFD procurement (10T Single Girder EOT Crane) → 33% · Vikram Singh
    Vikram: in progress
  • DFT check (30T Goliath Crane) → 0% · Team
    Deepak: not done (drawing revision pending from design) · Pooja: not done (material not received yet)

Overdue & blockers

  • 🚧 Cutting plan & nesting — material not received yet; drawing revision pending from design
  • 🚧 Dimensional check — machine was down, maintenance came today; vendor promised supply by tomorrow; machine was down, maintenance came today
  • 🚧 Plate & section procurement — final welding still pending
  • 🚧 Wheel turning & boring — operator was on leave
  • 🚧 DFT check — drawing revision pending from design; material not received yet
  • Cutting plan & nesting · 20T Double Girder EOT Crane · due 10 Oct · 50%
    📝 Imran: drawing revision pending from design
  • Wheel turning & boring · 20T Double Girder EOT Crane · due 15 Oct · 50%
    📝 Mahesh: operator was on leave
  • Dimensional check · 20T Double Girder EOT Crane · due 15 Oct · 50%
    📝 Pooja: machine was down, maintenance came today

Reasons given

  • Cutting plan & nesting (20T Double Girder EOT Crane)
    Suresh Yadav: “material not received yet”
  • Dimensional check (20T Double Girder EOT Crane)
    Suresh Yadav: “machine was down, maintenance came today”
  • Plate & section procurement (10T Single Girder EOT Crane)
    Suresh Yadav: “final welding still pending”
  • Cutting plan & nesting (20T Double Girder EOT Crane)
    Imran Khan: “drawing revision pending from design”
  • Dimensional check (20T Double Girder EOT Crane)
    Imran Khan: “vendor promised supply by tomorrow”
  • Wheel turning & boring (20T Double Girder EOT Crane)
    Mahesh Patil: “operator was on leave”
  • DFT check (30T Goliath Crane)
    Deepak Kumar: “drawing revision pending from design”
  • DFT check (30T Goliath Crane)
    Pooja Nair: “material not received yet”
  • Dimensional check (20T Double Girder EOT Crane)
    Pooja Nair: “machine was down, maintenance came today”

Answers differ

Co-workers disagreed — these tasks were kept open.

  • Plate & section procurement (10T Single Girder EOT Crane)
    Suresh Yadav: not done, Imran Khan: done

No reply

Everyone replied. 🎉