Production report — 16 Oct
8/59 tasks complete (14%). 7 in progress, 44 not started, 0 blocked.
Today: 1 task(s) completed · replies from 6/6 people followed up.
⚠️ 3 overdue: Cutting plan & nesting (20T Double Girder EOT Crane, 50%) — Imran: drawing revision pending from design; Wheel turning & boring (20T Double Girder EOT Crane, 50%) — Mahesh: operator was on leave; Dimensional check (20T Double Girder EOT Crane, 50%) — Pooja: machine was down, maintenance came today
📝 Reasons given: Cutting plan & nesting — Suresh Yadav: vendor promised supply by tomorrow; Dimensional check — Suresh Yadav: operator was on leave; Cutting plan & nesting — Imran Khan: shop crane was busy on another job; Dimensional check — Imran Khan: material not received yet; Wheel turning & boring — Mahesh Patil: machine was down, maintenance came today; DFT check — Deepak Kumar: shop crane was busy on another job
• Painting: 0/9 done, avg 0%
• Dispatch: 0/6 done, avg 0%
• Machining: 3/10 done, avg 40%, 1 overdue
• Fabrication: 3/21 done, avg 23%, 2 overdue
• Electrical: 2/13 done, avg 23%
Complete
8/59
Completed today
1
Overdue
3
Replies
6/6

By work

Painting0/9 · 0%
Dispatch0/6 · 0%
Machining3/10 · 40% · 1 overdue
Fabrication3/21 · 23% · 2 overdue
Electrical2/13 · 23%

Today's updates

  • Cutting plan & nesting (20T Double Girder EOT Crane) → 50% · Team
    Suresh: not done (vendor promised supply by tomorrow) · Imran: not done (shop crane was busy on another job)
  • Dimensional check (20T Double Girder EOT Crane) → 50% · Team
    Suresh: not done (operator was on leave) · Imran: not done (material not received yet) · Pooja: not done (operator was on leave)
  • Girder fit-up & welding (20T Double Girder EOT Crane) → 75% · Team
    Suresh: in progress · Imran: in progress
  • Wheel turning & boring (20T Double Girder EOT Crane) → 50% · Mahesh Patil
    Mahesh: not done (machine was down, maintenance came today)
  • Drum grooving (20T Double Girder EOT Crane) → 100% · Mahesh Patil
    Marked done — Mahesh: done
  • Wheel & bearing assembly (20T Double Girder EOT Crane) → 50% · Mahesh Patil
    Mahesh: in progress
  • Panel wiring (20T Double Girder EOT Crane) → 67% · Vikram Singh
    Vikram: in progress
  • Festoon cabling & trolleys (20T Double Girder EOT Crane) → 33% · Vikram Singh
    Vikram: in progress
  • DFT check (30T Goliath Crane) → 0% · Team
    Deepak: not done (shop crane was busy on another job) · Pooja: not done (vendor promised supply by tomorrow)

Overdue & blockers

  • 🚧 Cutting plan & nesting — vendor promised supply by tomorrow; shop crane was busy on another job
  • 🚧 Dimensional check — operator was on leave; material not received yet; operator was on leave
  • 🚧 Wheel turning & boring — machine was down, maintenance came today
  • 🚧 DFT check — shop crane was busy on another job; vendor promised supply by tomorrow
  • Cutting plan & nesting · 20T Double Girder EOT Crane · due 10 Oct · 50%
    📝 Imran: drawing revision pending from design
  • Wheel turning & boring · 20T Double Girder EOT Crane · due 15 Oct · 50%
    📝 Mahesh: operator was on leave
  • Dimensional check · 20T Double Girder EOT Crane · due 15 Oct · 50%
    📝 Pooja: machine was down, maintenance came today

Reasons given

  • Cutting plan & nesting (20T Double Girder EOT Crane)
    Suresh Yadav: “vendor promised supply by tomorrow”
  • Dimensional check (20T Double Girder EOT Crane)
    Suresh Yadav: “operator was on leave”
  • Cutting plan & nesting (20T Double Girder EOT Crane)
    Imran Khan: “shop crane was busy on another job”
  • Dimensional check (20T Double Girder EOT Crane)
    Imran Khan: “material not received yet”
  • Wheel turning & boring (20T Double Girder EOT Crane)
    Mahesh Patil: “machine was down, maintenance came today”
  • DFT check (30T Goliath Crane)
    Deepak Kumar: “shop crane was busy on another job”
  • DFT check (30T Goliath Crane)
    Pooja Nair: “vendor promised supply by tomorrow”
  • Dimensional check (20T Double Girder EOT Crane)
    Pooja Nair: “operator was on leave”

Answers differ

Co-workers disagreed — these tasks were kept open.

No conflicting answers.

No reply

Everyone replied. 🎉