Production dashboard
21 Oct · 2 active projects
Progress by work
Projects
Overdue & due today
View all →- Cutting plan & nestingEOT-2026-041 · Main Girder (Box Type) · Imran Khan, Suresh YadavOverduedue 10 Oct · 50%
- Shaft machiningEOT-2026-041 · Wheel Assembly · Mahesh PatilOverduedue 14 Oct · 67%
- Dimensional checkEOT-2026-041 · End Carriage · Imran Khan, Pooja Nair, Suresh YadavOverduedue 15 Oct · 50%
- Panel GA & wiring drawingEOT-2026-047 · Control Panel · Vikram SinghOverduedue 19 Oct · 50%
- Panel testingEOT-2026-041 · Control Panel · Vikram SinghOverduedue 20 Oct · 67%
- Weld inspection (DPT/UT)EOT-2026-041 · Main Girder (Box Type) · Imran Khan, Pooja Nair, Suresh YadavDue todaydue 21 Oct · 33%
Latest updates from the floor
WhatsApp log →- Dimensional checkBlocked
Imran: not done (operator chutti pe tha) · Pooja: not done (drawing revision pending hai design se)
🚧 Imran: operator chutti pe tha; Pooja: drawing revision pending hai design se
🤖 AI · Dashboard · EOT-2026-041 · 50% · 21 Oct, 12:46 pm - End carriage fabricationIn progress
Imran: in progress · Suresh: in progress
🤖 AI · Dashboard · EOT-2026-047 · 50% · 21 Oct, 12:46 pm - Cutting & web/flange prepIn progress
Imran: in progress
🤖 AI · Imran Khan · EOT-2026-047 · 25% · 21 Oct, 12:46 pm - Weld inspection (DPT/UT)In progress
Kept open — answers differ (Imran: done · Suresh: not done (final welding baaki hai) · Pooja: not done (final welding baaki hai))
🚧 Suresh: final welding baaki hai; Pooja: final welding baaki hai
🤖 AI · Dashboard · EOT-2026-041 · 33% · 21 Oct, 12:46 pm - Shaft machiningBlocked
Mahesh: not done (crane free nahi thi, dusre job pe lagi thi)
🚧 Mahesh: crane free nahi thi, dusre job pe lagi thi
🤖 AI · Mahesh Patil · EOT-2026-041 · 67% · 21 Oct, 12:46 pm - Cutting plan & nestingBlocked
Imran: not done (vendor ne supply kal tak bola hai) · Suresh: not done (machine kharab thi, maintenance wale aaj aaye)
🚧 Imran: vendor ne supply kal tak bola hai; Suresh: machine kharab thi, maintenance wale aaj aaye
🤖 AI · Dashboard · EOT-2026-041 · 50% · 21 Oct, 12:46 pm - DFT checkBlocked
Pooja: not done (machine kharab thi, maintenance wale aaj aaye) · Deepak: not done (vendor ne supply kal tak bola hai)
🚧 Pooja: machine kharab thi, maintenance wale aaj aaye; Deepak: vendor ne supply kal tak bola hai
🤖 AI · Dashboard · GC-2026-033 · 0% · 21 Oct, 12:46 pm - Cutting plan & nestingIn progress
Suresh: not done (material not received yet) · Imran: not done (drawing revision pending from design)
🚧 material not received yet; drawing revision pending from design
🤖 AI · Dashboard · EOT-2026-041 · 50% · 20 Oct, 09:00 pm
Latest daily report · 20 Oct
All reports →Production report — 20 Oct 16/59 tasks complete (27%). 8 in progress, 35 not started, 0 blocked. Today: 3 task(s) completed · replies from 6/6 people followed up. ⚠️ 4 overdue: Cutting plan & nesting (20T Double Girder EOT Crane, 50%) — Imran: drawing revision pending from design; Shaft machining (20T Double Girder EOT Crane, 67%) — Mahesh: operator was on leave; Dimensional check (20T Double Girder EOT Crane, 50%) — Pooja: machine was down, maintenance came today; Panel GA & wiring drawing (10T Single Girder EOT Crane, 50%) — Vikram: material not received yet 📝 Reasons given: Cutting plan & nesting — Suresh Yadav: material not received yet; Dimensional check — Suresh Yadav: machine was down, maintenance came today; End carriage fabrication — Suresh Yadav: final welding still pending; Cutting plan & nesting — Imran Khan: drawing revision pending from design; Dimensional check — Imran Khan: vendor promised supply by tomorrow; Shaft machining — Mahesh Patil: operator was on leave ↔️ Answers differ (kept open): End carriage fabrication — Suresh Yadav: not done, Imran Khan: done • Dispatch: 0/6 done, avg 0% • Electrical: 4/13 done, avg 42%, 1 overdue • Painting: 0/9 done, avg 0% • Machining: 6/10 done, avg 67%, 1 overdue • Fabrication: 6/21 done, avg 36%, 2 overdue