| Task | Project / component | Assigned | Dates | Status | Progress |
|---|---|---|---|---|---|
| DFT checkQuality Check | GC-2026-033 Girder Painting | Deepak Kumar, Pooja Nair | 27 Sept → 27 Sept | BlockedOverdue | 0% |
| Cutting plan & nestingPlanning | EOT-2026-041 Main Girder (Box Type) | Suresh Yadav, Imran Khan | 09 Oct → 10 Oct | BlockedOverdue | 50% |
| Dimensional checkQuality Check | EOT-2026-041 End Carriage | Suresh Yadav, Imran Khan, Pooja Nair | 15 Oct → 15 Oct | BlockedOverdue | 50% |
| Wheel turning & boringProduction | EOT-2026-041 Wheel Assembly | Mahesh Patil | 12 Oct → 15 Oct | In progressOverdue | 50% |
| Panel testingTesting | EOT-2026-041 Control Panel | Vikram Singh | 19 Oct → 20 Oct | In progressOverdue | 67% |
| Plate & section procurementProcurement | EOT-2026-047 Main Girder (Box Type) | Suresh Yadav, Imran Khan | 17 Oct → 20 Oct | In progressOverdue | 67% |
| Cutting & web/flange prepProduction | EOT-2026-047 Main Girder (Box Type) | Suresh Yadav, Imran Khan | 21 Oct → 23 Oct | PendingAt risk | 0% |
| Shot blasting (SA 2.5)Production | EOT-2026-041 Girder Painting | Deepak Kumar | 22 Oct → 23 Oct | PendingUpcoming | 0% |
| Switchgear & VFD procurementProcurement | EOT-2026-047 Control Panel | Vikram Singh | 19 Oct → 24 Oct | In progressOn track | 33% |
| End carriage fabricationProduction | EOT-2026-047 End Carriage | Suresh Yadav, Imran Khan | 20 Oct → 24 Oct | In progressOn track | 25% |
| Shaft machiningProduction | EOT-2026-047 Wheel Assembly | Mahesh Patil | 22 Oct → 24 Oct | PendingUpcoming | 0% |
| Wheel turning & boringProduction | EOT-2026-047 Wheel Assembly | Mahesh Patil | 22 Oct → 25 Oct | PendingUpcoming | 0% |
| Dimensional checkQuality Check | EOT-2026-047 End Carriage | Suresh Yadav, Imran Khan, Pooja Nair | 25 Oct → 25 Oct | PendingUpcoming | 0% |
| Wheel & bearing assemblyAssembly | EOT-2026-047 Wheel Assembly | Mahesh Patil | 26 Oct → 27 Oct | PendingUpcoming | 0% |
| Primer + intermediate + finish coatsProduction | EOT-2026-041 Girder Painting | Deepak Kumar | 24 Oct → 27 Oct | PendingUpcoming | 0% |
| DFT checkQuality Check | EOT-2026-041 Girder Painting | Deepak Kumar, Pooja Nair | 28 Oct → 28 Oct | PendingUpcoming | 0% |
| Panel wiringAssembly | EOT-2026-047 Control Panel | Vikram Singh | 25 Oct → 28 Oct | PendingUpcoming | 0% |
| Dispatch documentsDocumentation | EOT-2026-041 Dispatch Package | Ramesh Gupta | 27 Oct → 28 Oct | PendingUpcoming | 0% |
| Panel GA & wiring drawingDrawing / Design | UC-2026-052 Control Panel | Vikram Singh | 26 Oct → 28 Oct | PendingUpcoming | 0% |
| Plate & section procurementProcurement | UC-2026-052 Main Girder (Box Type) | Suresh Yadav, Imran Khan | 26 Oct → 29 Oct | PendingUpcoming | 0% |
| Cutting plan & nestingPlanning | UC-2026-052 Main Girder (Box Type) | Suresh Yadav, Imran Khan | 28 Oct → 29 Oct | PendingUpcoming | 0% |
| Girder fit-up & weldingAssembly | EOT-2026-047 Main Girder (Box Type) | Suresh Yadav, Imran Khan | 24 Oct → 29 Oct | PendingUpcoming | 0% |
| Panel testingTesting | EOT-2026-047 Control Panel | Vikram Singh | 29 Oct → 30 Oct | PendingUpcoming | 0% |
| Packing & loadingProduction | EOT-2026-041 Dispatch Package | Ramesh Gupta | 29 Oct → 30 Oct | PendingUpcoming | 0% |
| Weld inspection (DPT/UT)Quality Check | EOT-2026-047 Main Girder (Box Type) | Suresh Yadav, Imran Khan, Pooja Nair | 30 Oct → 31 Oct | PendingUpcoming | 0% |
| Cutting & web/flange prepProduction | UC-2026-052 Main Girder (Box Type) | Suresh Yadav, Imran Khan | 30 Oct → 01 Nov | PendingUpcoming | 0% |
| End carriage fabricationProduction | UC-2026-052 End Carriage | Suresh Yadav, Imran Khan | 29 Oct → 02 Nov | PendingUpcoming | 0% |
| Shot blasting (SA 2.5)Production | EOT-2026-047 Girder Painting | Deepak Kumar | 01 Nov → 02 Nov | PendingUpcoming | 0% |
| Switchgear & VFD procurementProcurement | UC-2026-052 Control Panel | Vikram Singh | 28 Oct → 02 Nov | PendingUpcoming | 0% |
| Dimensional checkQuality Check | UC-2026-052 End Carriage | Suresh Yadav, Imran Khan, Pooja Nair | 03 Nov → 03 Nov | PendingUpcoming | 0% |
| Panel wiringAssembly | UC-2026-052 Control Panel | Vikram Singh | 03 Nov → 06 Nov | PendingUpcoming | 0% |
| Primer + intermediate + finish coatsProduction | EOT-2026-047 Girder Painting | Deepak Kumar | 03 Nov → 06 Nov | PendingUpcoming | 0% |
| Dispatch documentsDocumentation | EOT-2026-047 Dispatch Package | Ramesh Gupta | 06 Nov → 07 Nov | PendingUpcoming | 0% |
| DFT checkQuality Check | EOT-2026-047 Girder Painting | Deepak Kumar, Pooja Nair | 07 Nov → 07 Nov | PendingUpcoming | 0% |
| Girder fit-up & weldingAssembly | UC-2026-052 Main Girder (Box Type) | Suresh Yadav, Imran Khan | 02 Nov → 07 Nov | PendingUpcoming | 0% |
| Panel testingTesting | UC-2026-052 Control Panel | Vikram Singh | 07 Nov → 08 Nov | PendingUpcoming | 0% |
| Weld inspection (DPT/UT)Quality Check | UC-2026-052 Main Girder (Box Type) | Suresh Yadav, Imran Khan, Pooja Nair | 08 Nov → 09 Nov | PendingUpcoming | 0% |
| Packing & loadingProduction | EOT-2026-047 Dispatch Package | Ramesh Gupta | 08 Nov → 09 Nov | PendingUpcoming | 0% |
| Shot blasting (SA 2.5)Production | UC-2026-052 Girder Painting | Deepak Kumar | 10 Nov → 11 Nov | PendingUpcoming | 0% |
| Primer + intermediate + finish coatsProduction | UC-2026-052 Girder Painting | Deepak Kumar | 12 Nov → 15 Nov | PendingUpcoming | 0% |
| DFT checkQuality Check | UC-2026-052 Girder Painting | Deepak Kumar, Pooja Nair | 16 Nov → 16 Nov | PendingUpcoming | 0% |
| Dispatch documentsDocumentation | UC-2026-052 Dispatch Package | Ramesh Gupta | 15 Nov → 16 Nov | PendingUpcoming | 0% |
| Packing & loadingProduction | UC-2026-052 Dispatch Package | Ramesh Gupta | 17 Nov → 18 Nov | PendingUpcoming | 0% |