PTProTaskProduction tracker

Daily reports

Generated every evening from the day's WhatsApp updates. Managers flagged in Employees get it on WhatsApp.

14 Oct · generated 14 Oct, 09:05 pm (cron)
Production report — 14 Oct
7/59 tasks complete (12%). 4 in progress, 48 not started, 0 blocked.
Today: 3 task(s) completed · replies from 5/6 people followed up.
⚠️ 1 overdue: Cutting plan & nesting (20T Double Girder EOT Crane, 50%) — Imran: drawing revision pending from design
📝 Reasons given: Cutting plan & nesting — Imran Khan: vendor promised supply by tomorrow; DFT check — Deepak Kumar: vendor promised supply by tomorrow; DFT check — Pooja Nair: machine was down, maintenance came today
🔕 No reply: Suresh Yadav
• Painting: 0/9 done, avg 0%
• Dispatch: 0/6 done, avg 0%
• Machining: 2/10 done, avg 29%
• Fabrication: 3/21 done, avg 18%, 1 overdue
• Electrical: 2/13 done, avg 15%
Complete
7/59
Completed today
3
Overdue
1
Replies
5/6

By work

Painting0/9 · 0%
Dispatch0/6 · 0%
Machining2/10 · 29%
Fabrication3/21 · 18% · 1 overdue
Electrical2/13 · 15%

Today's updates

  • Cutting plan & nesting (20T Double Girder EOT Crane) → 50% · Imran Khan
    Imran: not done (vendor promised supply by tomorrow)
  • End carriage fabrication (20T Double Girder EOT Crane) → 100% · Imran Khan
    Marked done — Imran: done
  • Girder fit-up & welding (20T Double Girder EOT Crane) → 25% · Imran Khan
    Imran: in progress
  • Shaft machining (20T Double Girder EOT Crane) → 100% · Mahesh Patil
    Marked done — Mahesh: done
  • Drum grooving (20T Double Girder EOT Crane) → 67% · Mahesh Patil
    Mahesh: in progress
  • Switchgear & VFD procurement (20T Double Girder EOT Crane) → 100% · Vikram Singh
    Marked done — Vikram: done
  • DFT check (30T Goliath Crane) → 0% · Team
    Deepak: not done (vendor promised supply by tomorrow) · Pooja: not done (machine was down, maintenance came today)

Overdue & blockers

  • 🚧 Cutting plan & nesting — vendor promised supply by tomorrow
  • 🚧 DFT check — vendor promised supply by tomorrow; machine was down, maintenance came today
  • Cutting plan & nesting · 20T Double Girder EOT Crane · due 10 Oct · 50%
    📝 Imran: drawing revision pending from design

Reasons given

  • Cutting plan & nesting (20T Double Girder EOT Crane)
    Imran Khan: “vendor promised supply by tomorrow”
  • DFT check (30T Goliath Crane)
    Deepak Kumar: “vendor promised supply by tomorrow”
  • DFT check (30T Goliath Crane)
    Pooja Nair: “machine was down, maintenance came today”

Answers differ

Co-workers disagreed — these tasks were kept open.

No conflicting answers.

No reply

  • Suresh Yadav