Daily reports
Generated every evening from the day's WhatsApp updates. Managers flagged in Employees get it on WhatsApp.
15 Oct · generated 15 Oct, 09:05 pm (cron)
Production report — 15 Oct 7/59 tasks complete (12%). 6 in progress, 46 not started, 0 blocked. Today: 0 task(s) completed · replies from 5/6 people followed up. ⚠️ 1 overdue: Cutting plan & nesting (20T Double Girder EOT Crane, 50%) — Imran: drawing revision pending from design 📝 Reasons given: Cutting plan & nesting — Suresh Yadav: drawing revision pending from design; DFT check — Deepak Kumar: operator was on leave; DFT check — Pooja Nair: drawing revision pending from design 🔕 No reply: Imran Khan • Painting: 0/9 done, avg 0% • Dispatch: 0/6 done, avg 0% • Machining: 2/10 done, avg 32% • Fabrication: 3/21 done, avg 21%, 1 overdue • Electrical: 2/13 done, avg 18%
Complete
7/59
Completed today
0
Overdue
1
Replies
5/6
By work
Painting0/9 · 0%
Dispatch0/6 · 0%
Machining2/10 · 32%
Fabrication3/21 · 21% · 1 overdue
Electrical2/13 · 18%
Today's updates
- Cutting plan & nesting (20T Double Girder EOT Crane) → 50% · Suresh YadavSuresh: not done (drawing revision pending from design)
- Dimensional check (20T Double Girder EOT Crane) → 50% · TeamSuresh: in progress · Pooja: in progress
- Girder fit-up & welding (20T Double Girder EOT Crane) → 50% · Suresh YadavSuresh: in progress
- Wheel turning & boring (20T Double Girder EOT Crane) → 50% · Mahesh PatilMahesh: in progress
- Panel wiring (20T Double Girder EOT Crane) → 33% · Vikram SinghVikram: in progress
- DFT check (30T Goliath Crane) → 0% · TeamDeepak: not done (operator was on leave) · Pooja: not done (drawing revision pending from design)
Overdue & blockers
- 🚧 Cutting plan & nesting — drawing revision pending from design
- 🚧 DFT check — operator was on leave; drawing revision pending from design
- Cutting plan & nesting · 20T Double Girder EOT Crane · due 10 Oct · 50%📝 Imran: drawing revision pending from design
Reasons given
- Cutting plan & nesting (20T Double Girder EOT Crane)Suresh Yadav: “drawing revision pending from design”
- DFT check (30T Goliath Crane)Deepak Kumar: “operator was on leave”
- DFT check (30T Goliath Crane)Pooja Nair: “drawing revision pending from design”
Answers differ
Co-workers disagreed — these tasks were kept open.
No conflicting answers.
No reply
- Imran Khan