Production report — 15 Oct
7/59 tasks complete (12%). 6 in progress, 46 not started, 0 blocked.
Today: 0 task(s) completed · replies from 5/6 people followed up.
⚠️ 1 overdue: Cutting plan & nesting (20T Double Girder EOT Crane, 50%) — Imran: drawing revision pending from design
📝 Reasons given: Cutting plan & nesting — Suresh Yadav: drawing revision pending from design; DFT check — Deepak Kumar: operator was on leave; DFT check — Pooja Nair: drawing revision pending from design
🔕 No reply: Imran Khan
• Painting: 0/9 done, avg 0%
• Dispatch: 0/6 done, avg 0%
• Machining: 2/10 done, avg 32%
• Fabrication: 3/21 done, avg 21%, 1 overdue
• Electrical: 2/13 done, avg 18%
Complete
7/59
Completed today
0
Overdue
1
Replies
5/6

By work

Painting0/9 · 0%
Dispatch0/6 · 0%
Machining2/10 · 32%
Fabrication3/21 · 21% · 1 overdue
Electrical2/13 · 18%

Today's updates

  • Cutting plan & nesting (20T Double Girder EOT Crane) → 50% · Suresh Yadav
    Suresh: not done (drawing revision pending from design)
  • Dimensional check (20T Double Girder EOT Crane) → 50% · Team
    Suresh: in progress · Pooja: in progress
  • Girder fit-up & welding (20T Double Girder EOT Crane) → 50% · Suresh Yadav
    Suresh: in progress
  • Wheel turning & boring (20T Double Girder EOT Crane) → 50% · Mahesh Patil
    Mahesh: in progress
  • Panel wiring (20T Double Girder EOT Crane) → 33% · Vikram Singh
    Vikram: in progress
  • DFT check (30T Goliath Crane) → 0% · Team
    Deepak: not done (operator was on leave) · Pooja: not done (drawing revision pending from design)

Overdue & blockers

  • 🚧 Cutting plan & nesting — drawing revision pending from design
  • 🚧 DFT check — operator was on leave; drawing revision pending from design
  • Cutting plan & nesting · 20T Double Girder EOT Crane · due 10 Oct · 50%
    📝 Imran: drawing revision pending from design

Reasons given

  • Cutting plan & nesting (20T Double Girder EOT Crane)
    Suresh Yadav: “drawing revision pending from design”
  • DFT check (30T Goliath Crane)
    Deepak Kumar: “operator was on leave”
  • DFT check (30T Goliath Crane)
    Pooja Nair: “drawing revision pending from design”

Answers differ

Co-workers disagreed — these tasks were kept open.

No conflicting answers.

No reply

  • Imran Khan