13 Oct · generated 13 Oct, 09:05 pm (cron)
Production report — 13 Oct
4/59 tasks complete (7%). 6 in progress, 49 not started, 0 blocked.
Today: 1 task(s) completed · replies from 6/6 people followed up.
⚠️ 1 overdue: Cutting plan & nesting (20T Double Girder EOT Crane, 50%) — Imran: drawing revision pending from design
📝 Reasons given: Cutting plan & nesting — Suresh Yadav: material not received yet; Cutting plan & nesting — Imran Khan: drawing revision pending from design; DFT check — Deepak Kumar: drawing revision pending from design; DFT check — Pooja Nair: material not received yet
• Painting: 0/9 done, avg 0%
• Dispatch: 0/6 done, avg 0%
• Machining: 1/10 done, avg 23%
• Fabrication: 2/21 done, avg 15%, 1 overdue
• Electrical: 1/13 done, avg 13%
Complete
4/59
Completed today
1
Overdue
1
Replies
6/6

By work

Painting0/9 · 0%
Dispatch0/6 · 0%
Machining1/10 · 23%
Fabrication2/21 · 15% · 1 overdue
Electrical1/13 · 13%

Today's updates

  • Cutting plan & nesting (20T Double Girder EOT Crane) → 50% · Team
    Suresh: not done (material not received yet) · Imran: not done (drawing revision pending from design)
  • Cutting & web/flange prep (20T Double Girder EOT Crane) → 100% · Team
    Marked done — Suresh: done · Imran: done
  • End carriage fabrication (20T Double Girder EOT Crane) → 75% · Team
    Suresh: in progress · Imran: in progress
  • Shaft machining (20T Double Girder EOT Crane) → 67% · Mahesh Patil
    Mahesh: in progress
  • Wheel turning & boring (20T Double Girder EOT Crane) → 25% · Mahesh Patil
    Mahesh: in progress
  • Drum grooving (20T Double Girder EOT Crane) → 33% · Mahesh Patil
    Mahesh: in progress
  • DFT check (30T Goliath Crane) → 0% · Team
    Deepak: not done (drawing revision pending from design) · Pooja: not done (material not received yet)

Overdue & blockers

  • 🚧 Cutting plan & nesting — material not received yet; drawing revision pending from design
  • 🚧 DFT check — drawing revision pending from design; material not received yet
  • Cutting plan & nesting · 20T Double Girder EOT Crane · due 10 Oct · 50%
    📝 Imran: drawing revision pending from design

Reasons given

  • Cutting plan & nesting (20T Double Girder EOT Crane)
    Suresh Yadav: “material not received yet”
  • Cutting plan & nesting (20T Double Girder EOT Crane)
    Imran Khan: “drawing revision pending from design”
  • DFT check (30T Goliath Crane)
    Deepak Kumar: “drawing revision pending from design”
  • DFT check (30T Goliath Crane)
    Pooja Nair: “material not received yet”

Answers differ

Co-workers disagreed — these tasks were kept open.

No conflicting answers.

No reply

Everyone replied. 🎉