13 Oct · generated 13 Oct, 09:05 pm (cron)
Production report — 13 Oct 4/59 tasks complete (7%). 6 in progress, 49 not started, 0 blocked. Today: 1 task(s) completed · replies from 6/6 people followed up. ⚠️ 1 overdue: Cutting plan & nesting (20T Double Girder EOT Crane, 50%) — Imran: drawing revision pending from design 📝 Reasons given: Cutting plan & nesting — Suresh Yadav: material not received yet; Cutting plan & nesting — Imran Khan: drawing revision pending from design; DFT check — Deepak Kumar: drawing revision pending from design; DFT check — Pooja Nair: material not received yet • Painting: 0/9 done, avg 0% • Dispatch: 0/6 done, avg 0% • Machining: 1/10 done, avg 23% • Fabrication: 2/21 done, avg 15%, 1 overdue • Electrical: 1/13 done, avg 13%
Complete
4/59
Completed today
1
Overdue
1
Replies
6/6
By work
Painting0/9 · 0%
Dispatch0/6 · 0%
Machining1/10 · 23%
Fabrication2/21 · 15% · 1 overdue
Electrical1/13 · 13%
Today's updates
- Cutting plan & nesting (20T Double Girder EOT Crane) → 50% · TeamSuresh: not done (material not received yet) · Imran: not done (drawing revision pending from design)
- Cutting & web/flange prep (20T Double Girder EOT Crane) → 100% · TeamMarked done — Suresh: done · Imran: done
- End carriage fabrication (20T Double Girder EOT Crane) → 75% · TeamSuresh: in progress · Imran: in progress
- Shaft machining (20T Double Girder EOT Crane) → 67% · Mahesh PatilMahesh: in progress
- Wheel turning & boring (20T Double Girder EOT Crane) → 25% · Mahesh PatilMahesh: in progress
- Drum grooving (20T Double Girder EOT Crane) → 33% · Mahesh PatilMahesh: in progress
- DFT check (30T Goliath Crane) → 0% · TeamDeepak: not done (drawing revision pending from design) · Pooja: not done (material not received yet)
Overdue & blockers
- 🚧 Cutting plan & nesting — material not received yet; drawing revision pending from design
- 🚧 DFT check — drawing revision pending from design; material not received yet
- Cutting plan & nesting · 20T Double Girder EOT Crane · due 10 Oct · 50%📝 Imran: drawing revision pending from design
Reasons given
- Cutting plan & nesting (20T Double Girder EOT Crane)Suresh Yadav: “material not received yet”
- Cutting plan & nesting (20T Double Girder EOT Crane)Imran Khan: “drawing revision pending from design”
- DFT check (30T Goliath Crane)Deepak Kumar: “drawing revision pending from design”
- DFT check (30T Goliath Crane)Pooja Nair: “material not received yet”
Answers differ
Co-workers disagreed — these tasks were kept open.
No conflicting answers.
No reply
Everyone replied. 🎉