Production report — 19 Oct
14/59 tasks complete (24%). 7 in progress, 38 not started, 0 blocked.
Today: 2 task(s) completed · replies from 6/6 people followed up.
⚠️ 3 overdue: Cutting plan & nesting (20T Double Girder EOT Crane, 50%) — Imran: drawing revision pending from design; Wheel turning & boring (20T Double Girder EOT Crane, 50%) — Mahesh: operator was on leave; Dimensional check (20T Double Girder EOT Crane, 50%) — Pooja: machine was down, maintenance came today
📝 Reasons given: Cutting plan & nesting — Suresh Yadav: shop crane was busy on another job; Dimensional check — Suresh Yadav: material not received yet; Cutting plan & nesting — Imran Khan: machine was down, maintenance came today; Dimensional check — Imran Khan: drawing revision pending from design; Wheel turning & boring — Mahesh Patil: vendor promised supply by tomorrow; DFT check — Deepak Kumar: machine was down, maintenance came today
• Painting: 0/9 done, avg 0%
• Dispatch: 0/6 done, avg 0%
• Machining: 5/10 done, avg 60%, 1 overdue
• Fabrication: 4/21 done, avg 28%, 2 overdue
• Electrical: 5/13 done, avg 41%
Complete
14/59
Completed today
2
Overdue
3
Replies
6/6

By work

Painting0/9 · 0%
Dispatch0/6 · 0%
Machining5/10 · 60% · 1 overdue
Fabrication4/21 · 28% · 2 overdue
Electrical5/13 · 41%

Today's updates

  • Cutting plan & nesting (20T Double Girder EOT Crane) → 50% · Team
    Suresh: not done (shop crane was busy on another job) · Imran: not done (machine was down, maintenance came today)
  • Dimensional check (20T Double Girder EOT Crane) → 50% · Team
    Suresh: not done (material not received yet) · Imran: not done (drawing revision pending from design) · Pooja: not done (material not received yet)
  • Girder fit-up & welding (20T Double Girder EOT Crane) → 100% · Team
    Marked done — Suresh: done · Imran: done
  • Cutting plan & nesting (10T Single Girder EOT Crane) → 50% · Team
    Suresh: in progress · Imran: in progress
  • Wheel turning & boring (20T Double Girder EOT Crane) → 50% · Mahesh Patil
    Mahesh: not done (vendor promised supply by tomorrow)
  • Panel GA & wiring drawing (10T Single Girder EOT Crane) → 100% · Vikram Singh
    Marked done — Vikram: done
  • Panel testing (20T Double Girder EOT Crane) → 33% · Vikram Singh
    Vikram: in progress
  • DFT check (30T Goliath Crane) → 0% · Team
    Deepak: not done (machine was down, maintenance came today) · Pooja: not done (shop crane was busy on another job)

Overdue & blockers

  • 🚧 Cutting plan & nesting — shop crane was busy on another job; machine was down, maintenance came today
  • 🚧 Dimensional check — material not received yet; drawing revision pending from design; material not received yet
  • 🚧 Wheel turning & boring — vendor promised supply by tomorrow
  • 🚧 DFT check — machine was down, maintenance came today; shop crane was busy on another job
  • Cutting plan & nesting · 20T Double Girder EOT Crane · due 10 Oct · 50%
    📝 Imran: drawing revision pending from design
  • Wheel turning & boring · 20T Double Girder EOT Crane · due 15 Oct · 50%
    📝 Mahesh: operator was on leave
  • Dimensional check · 20T Double Girder EOT Crane · due 15 Oct · 50%
    📝 Pooja: machine was down, maintenance came today

Reasons given

  • Cutting plan & nesting (20T Double Girder EOT Crane)
    Suresh Yadav: “shop crane was busy on another job”
  • Dimensional check (20T Double Girder EOT Crane)
    Suresh Yadav: “material not received yet”
  • Cutting plan & nesting (20T Double Girder EOT Crane)
    Imran Khan: “machine was down, maintenance came today”
  • Dimensional check (20T Double Girder EOT Crane)
    Imran Khan: “drawing revision pending from design”
  • Wheel turning & boring (20T Double Girder EOT Crane)
    Mahesh Patil: “vendor promised supply by tomorrow”
  • DFT check (30T Goliath Crane)
    Deepak Kumar: “machine was down, maintenance came today”
  • DFT check (30T Goliath Crane)
    Pooja Nair: “shop crane was busy on another job”
  • Dimensional check (20T Double Girder EOT Crane)
    Pooja Nair: “material not received yet”

Answers differ

Co-workers disagreed — these tasks were kept open.

No conflicting answers.

No reply