Daily reports
Generated every evening from the day's WhatsApp updates. Managers flagged in Employees get it on WhatsApp.
19 Oct · generated 19 Oct, 09:05 pm (cron)
Production report — 19 Oct 14/59 tasks complete (24%). 7 in progress, 38 not started, 0 blocked. Today: 2 task(s) completed · replies from 6/6 people followed up. ⚠️ 3 overdue: Cutting plan & nesting (20T Double Girder EOT Crane, 50%) — Imran: drawing revision pending from design; Wheel turning & boring (20T Double Girder EOT Crane, 50%) — Mahesh: operator was on leave; Dimensional check (20T Double Girder EOT Crane, 50%) — Pooja: machine was down, maintenance came today 📝 Reasons given: Cutting plan & nesting — Suresh Yadav: shop crane was busy on another job; Dimensional check — Suresh Yadav: material not received yet; Cutting plan & nesting — Imran Khan: machine was down, maintenance came today; Dimensional check — Imran Khan: drawing revision pending from design; Wheel turning & boring — Mahesh Patil: vendor promised supply by tomorrow; DFT check — Deepak Kumar: machine was down, maintenance came today • Painting: 0/9 done, avg 0% • Dispatch: 0/6 done, avg 0% • Machining: 5/10 done, avg 60%, 1 overdue • Fabrication: 4/21 done, avg 28%, 2 overdue • Electrical: 5/13 done, avg 41%
Complete
14/59
Completed today
2
Overdue
3
Replies
6/6
By work
Painting0/9 · 0%
Dispatch0/6 · 0%
Machining5/10 · 60% · 1 overdue
Fabrication4/21 · 28% · 2 overdue
Electrical5/13 · 41%
Today's updates
- Cutting plan & nesting (20T Double Girder EOT Crane) → 50% · TeamSuresh: not done (shop crane was busy on another job) · Imran: not done (machine was down, maintenance came today)
- Dimensional check (20T Double Girder EOT Crane) → 50% · TeamSuresh: not done (material not received yet) · Imran: not done (drawing revision pending from design) · Pooja: not done (material not received yet)
- Girder fit-up & welding (20T Double Girder EOT Crane) → 100% · TeamMarked done — Suresh: done · Imran: done
- Cutting plan & nesting (10T Single Girder EOT Crane) → 50% · TeamSuresh: in progress · Imran: in progress
- Wheel turning & boring (20T Double Girder EOT Crane) → 50% · Mahesh PatilMahesh: not done (vendor promised supply by tomorrow)
- Panel GA & wiring drawing (10T Single Girder EOT Crane) → 100% · Vikram SinghMarked done — Vikram: done
- Panel testing (20T Double Girder EOT Crane) → 33% · Vikram SinghVikram: in progress
- DFT check (30T Goliath Crane) → 0% · TeamDeepak: not done (machine was down, maintenance came today) · Pooja: not done (shop crane was busy on another job)
Overdue & blockers
- 🚧 Cutting plan & nesting — shop crane was busy on another job; machine was down, maintenance came today
- 🚧 Dimensional check — material not received yet; drawing revision pending from design; material not received yet
- 🚧 Wheel turning & boring — vendor promised supply by tomorrow
- 🚧 DFT check — machine was down, maintenance came today; shop crane was busy on another job
- Cutting plan & nesting · 20T Double Girder EOT Crane · due 10 Oct · 50%📝 Imran: drawing revision pending from design
- Wheel turning & boring · 20T Double Girder EOT Crane · due 15 Oct · 50%📝 Mahesh: operator was on leave
- Dimensional check · 20T Double Girder EOT Crane · due 15 Oct · 50%📝 Pooja: machine was down, maintenance came today
Reasons given
- Cutting plan & nesting (20T Double Girder EOT Crane)Suresh Yadav: “shop crane was busy on another job”
- Dimensional check (20T Double Girder EOT Crane)Suresh Yadav: “material not received yet”
- Cutting plan & nesting (20T Double Girder EOT Crane)Imran Khan: “machine was down, maintenance came today”
- Dimensional check (20T Double Girder EOT Crane)Imran Khan: “drawing revision pending from design”
- Wheel turning & boring (20T Double Girder EOT Crane)Mahesh Patil: “vendor promised supply by tomorrow”
- DFT check (30T Goliath Crane)Deepak Kumar: “machine was down, maintenance came today”
- DFT check (30T Goliath Crane)Pooja Nair: “shop crane was busy on another job”
- Dimensional check (20T Double Girder EOT Crane)Pooja Nair: “material not received yet”
Answers differ
Co-workers disagreed — these tasks were kept open.
No conflicting answers.
No reply
Everyone replied. 🎉