30T Goliath Crane

GC-2026-033 · JSW Steel — Dolvi · 30T double-leg goliath, span 30m — delivered

Progress
95%
Tasks done
19/20
Overdue
1
Blocked
1
Delivery
03 Oct
started 06 Sept

Fabrication

Main Girder (Box Type)
100%
Plate & section procurementProcurement
Suresh Yadav, Imran Khan · 3/3 checkpoints
Done
06 Sept → 09 Sept
Cutting plan & nestingPlanning
Suresh Yadav, Imran Khan · 2/2 checkpoints
Done
08 Sept → 09 Sept
Cutting & web/flange prepProduction
Suresh Yadav, Imran Khan · 4/4 checkpoints
Done
10 Sept → 12 Sept
Girder fit-up & weldingAssembly
Suresh Yadav, Imran Khan · 4/4 checkpoints
Done
13 Sept → 18 Sept
Weld inspection (DPT/UT)Quality Check
Suresh Yadav, Imran Khan, Pooja Nair · 3/3 checkpoints
Done
19 Sept → 20 Sept
End Carriage
100%
End carriage fabricationProduction
Suresh Yadav, Imran Khan · 4/4 checkpoints
Done
09 Sept → 13 Sept
Dimensional checkQuality Check
Suresh Yadav, Imran Khan, Pooja Nair · 2/2 checkpoints
Done
14 Sept → 14 Sept

Machining

Wheel Assembly
100%
Forged wheel blanksProcurement
Mahesh Patil · 2/2 checkpoints
Done
06 Sept → 10 Sept
Wheel turning & boringProduction
Mahesh Patil · 4/4 checkpoints
Done
11 Sept → 14 Sept
Shaft machiningProduction
Mahesh Patil · 3/3 checkpoints
Done
11 Sept → 13 Sept
Wheel & bearing assemblyAssembly
Mahesh Patil · 2/2 checkpoints
Done
15 Sept → 16 Sept

Electrical

Control Panel
100%
Panel GA & wiring drawingDrawing / Design
Vikram Singh · 2/2 checkpoints
Done
06 Sept → 08 Sept
Switchgear & VFD procurementProcurement
Vikram Singh · 3/3 checkpoints
Done
08 Sept → 13 Sept
Panel wiringAssembly
Vikram Singh · 3/3 checkpoints
Done
14 Sept → 17 Sept
Panel testingTesting
Vikram Singh · 3/3 checkpoints
Done
18 Sept → 19 Sept

Painting

Girder Painting
67%
Shot blasting (SA 2.5)Production
Deepak Kumar · 2/2 checkpoints
Done
21 Sept → 22 Sept
Primer + intermediate + finish coatsProduction
Deepak Kumar · 3/3 checkpoints
Done
23 Sept → 26 Sept
DFT checkQuality Check
Deepak Kumar, Pooja Nair · 0/2 checkpoints
📝 Pooja: material not received yet
BlockedOverdue
27 Sept → 27 Sept

Dispatch

Dispatch Package
100%
Dispatch documentsDocumentation
Ramesh Gupta · 4/4 checkpoints
Done
26 Sept → 27 Sept
Packing & loadingProduction
Ramesh Gupta · 4/4 checkpoints
Done
28 Sept → 29 Sept