5T Underslung Crane

UC-2026-052 · Mahindra — Chakan · 5T underslung, 3 bays, pendant control

Progress
0%
Tasks done
0/16
Overdue
0
Blocked
0
Delivery
22 Nov
started 26 Oct

Fabrication

Main Girder (Box Type)
0%
Plate & section procurementProcurement
Suresh Yadav, Imran Khan · 0/3 checkpoints
PendingUpcoming
26 Oct → 29 Oct
Cutting plan & nestingPlanning
Suresh Yadav, Imran Khan · 0/2 checkpoints
PendingUpcoming
28 Oct → 29 Oct
Cutting & web/flange prepProduction
Suresh Yadav, Imran Khan · 0/4 checkpoints
PendingUpcoming
30 Oct → 01 Nov
Girder fit-up & weldingAssembly
Suresh Yadav, Imran Khan · 0/4 checkpoints
PendingUpcoming
02 Nov → 07 Nov
Weld inspection (DPT/UT)Quality Check
Suresh Yadav, Imran Khan, Pooja Nair · 0/3 checkpoints
PendingUpcoming
08 Nov → 09 Nov
End Carriage
0%
End carriage fabricationProduction
Suresh Yadav, Imran Khan · 0/4 checkpoints
PendingUpcoming
29 Oct → 02 Nov
Dimensional checkQuality Check
Suresh Yadav, Imran Khan, Pooja Nair · 0/2 checkpoints
PendingUpcoming
03 Nov → 03 Nov

Electrical

Control Panel
0%
Panel GA & wiring drawingDrawing / Design
Vikram Singh · 0/2 checkpoints
PendingUpcoming
26 Oct → 28 Oct
Switchgear & VFD procurementProcurement
Vikram Singh · 0/3 checkpoints
PendingUpcoming
28 Oct → 02 Nov
Panel wiringAssembly
Vikram Singh · 0/3 checkpoints
PendingUpcoming
03 Nov → 06 Nov
Panel testingTesting
Vikram Singh · 0/3 checkpoints
PendingUpcoming
07 Nov → 08 Nov

Painting

Girder Painting
0%
Shot blasting (SA 2.5)Production
Deepak Kumar · 0/2 checkpoints
PendingUpcoming
10 Nov → 11 Nov
Primer + intermediate + finish coatsProduction
Deepak Kumar · 0/3 checkpoints
PendingUpcoming
12 Nov → 15 Nov
DFT checkQuality Check
Deepak Kumar, Pooja Nair · 0/2 checkpoints
PendingUpcoming
16 Nov → 16 Nov

Dispatch

Dispatch Package
0%
Dispatch documentsDocumentation
Ramesh Gupta · 0/4 checkpoints
PendingUpcoming
15 Nov → 16 Nov
Packing & loadingProduction
Ramesh Gupta · 0/4 checkpoints
PendingUpcoming
17 Nov → 18 Nov