PTProTaskProduction tracker
Projects

20T Double Girder EOT Crane

EOT-2026-041 · Tata Steel — Jamshedpur · 20/5T DG EOT, span 22.5m, VFD controls

Progress
70%
Tasks done
14/23
Overdue
4
Blocked
2
Delivery
02 Nov
started 07 Oct

Fabrication

Main Girder (Box Type)
90%
Plate & section procurementProcurement
Suresh Yadav, Imran Khan · 3/3 checkpoints
Done
07 Oct → 10 Oct
Cutting plan & nestingPlanning
Suresh Yadav, Imran Khan · 1/2 checkpoints
📝 Imran: drawing revision pending from design
BlockedOverdue
09 Oct → 10 Oct
Cutting & web/flange prepProduction
Suresh Yadav, Imran Khan · 4/4 checkpoints
Done
11 Oct → 13 Oct
Girder fit-up & weldingAssembly
Suresh Yadav, Imran Khan · 4/4 checkpoints
Done
14 Oct → 19 Oct
Weld inspection (DPT/UT)Quality Check
Suresh Yadav, Imran Khan, Pooja Nair · 3/3 checkpoints
Done
20 Oct → 21 Oct
End Carriage
75%
End carriage fabricationProduction
Suresh Yadav, Imran Khan · 4/4 checkpoints
Done
10 Oct → 14 Oct
Dimensional checkQuality Check
Suresh Yadav, Imran Khan, Pooja Nair · 1/2 checkpoints
📝 Pooja: machine was down, maintenance came today
BlockedOverdue
15 Oct → 15 Oct

Machining

Wheel Assembly
88%
Forged wheel blanksProcurement
Mahesh Patil · 2/2 checkpoints
Done
07 Oct → 11 Oct
Wheel turning & boringProduction
Mahesh Patil · 2/4 checkpoints
📝 Mahesh: operator was on leave
In progressOverdue
12 Oct → 15 Oct
Shaft machiningProduction
Mahesh Patil · 3/3 checkpoints
Done
12 Oct → 14 Oct
Wheel & bearing assemblyAssembly
Mahesh Patil · 2/2 checkpoints
Done
16 Oct → 17 Oct
Hoist Drum
100%
Drum groovingProduction
Mahesh Patil · 3/3 checkpoints
Done
13 Oct → 16 Oct
Groove profile inspectionQuality Check
Mahesh Patil, Pooja Nair · 2/2 checkpoints
Done
17 Oct → 17 Oct

Electrical

Control Panel
92%
Panel GA & wiring drawingDrawing / Design
Vikram Singh · 2/2 checkpoints
Done
07 Oct → 09 Oct
Switchgear & VFD procurementProcurement
Vikram Singh · 3/3 checkpoints
Done
09 Oct → 14 Oct
Panel wiringAssembly
Vikram Singh · 3/3 checkpoints
Done
15 Oct → 18 Oct
Panel testingTesting
Vikram Singh · 2/3 checkpoints
In progressOverdue
19 Oct → 20 Oct
DSL / Festoon System
100%
Festoon cabling & trolleysAssembly
Vikram Singh · 3/3 checkpoints
Done
16 Oct → 18 Oct

Painting

Girder Painting
0%
Shot blasting (SA 2.5)Production
Deepak Kumar · 0/2 checkpoints
PendingUpcoming
22 Oct → 23 Oct
Primer + intermediate + finish coatsProduction
Deepak Kumar · 0/3 checkpoints
PendingUpcoming
24 Oct → 27 Oct
DFT checkQuality Check
Deepak Kumar, Pooja Nair · 0/2 checkpoints
PendingUpcoming
28 Oct → 28 Oct

Dispatch

Dispatch Package
0%
Dispatch documentsDocumentation
Ramesh Gupta · 0/4 checkpoints
PendingUpcoming
27 Oct → 28 Oct
Packing & loadingProduction
Ramesh Gupta · 0/4 checkpoints
PendingUpcoming
29 Oct → 30 Oct