10T Single Girder EOT Crane
EOT-2026-047 · L&T Hazira · 10T SG EOT, span 16m
Progress
21%
Tasks done
3/20
Overdue
1
Blocked
0
Delivery
12 Nov
started 17 Oct
Fabrication
Main Girder (Box Type)
Plate & section procurementProcurement
Suresh Yadav, Imran Khan · 2/3 checkpoints
📝 Suresh: final welding still pending
In progressOverdue
17 Oct → 20 Oct
67%
Cutting plan & nestingPlanning
Suresh Yadav, Imran Khan · 2/2 checkpoints
Done
19 Oct → 20 Oct
100%
Cutting & web/flange prepProduction
Suresh Yadav, Imran Khan · 0/4 checkpoints
PendingAt risk
21 Oct → 23 Oct
0%
Girder fit-up & weldingAssembly
Suresh Yadav, Imran Khan · 0/4 checkpoints
PendingUpcoming
24 Oct → 29 Oct
0%
Weld inspection (DPT/UT)Quality Check
Suresh Yadav, Imran Khan, Pooja Nair · 0/3 checkpoints
PendingUpcoming
30 Oct → 31 Oct
0%
End Carriage
End carriage fabricationProduction
Suresh Yadav, Imran Khan · 1/4 checkpoints
In progressOn track
20 Oct → 24 Oct
25%
Dimensional checkQuality Check
Suresh Yadav, Imran Khan, Pooja Nair · 0/2 checkpoints
PendingUpcoming
25 Oct → 25 Oct
0%
Machining
Wheel Assembly
Forged wheel blanksProcurement
Mahesh Patil · 2/2 checkpoints
Done
17 Oct → 21 Oct
100%
Wheel turning & boringProduction
Mahesh Patil · 0/4 checkpoints
PendingUpcoming
22 Oct → 25 Oct
0%
Shaft machiningProduction
Mahesh Patil · 0/3 checkpoints
PendingUpcoming
22 Oct → 24 Oct
0%
Wheel & bearing assemblyAssembly
Mahesh Patil · 0/2 checkpoints
PendingUpcoming
26 Oct → 27 Oct
0%
Electrical
Control Panel
Panel GA & wiring drawingDrawing / Design
Vikram Singh · 2/2 checkpoints
Done
17 Oct → 19 Oct
100%
Switchgear & VFD procurementProcurement
Vikram Singh · 1/3 checkpoints
In progressOn track
19 Oct → 24 Oct
33%
Panel wiringAssembly
Vikram Singh · 0/3 checkpoints
PendingUpcoming
25 Oct → 28 Oct
0%
Panel testingTesting
Vikram Singh · 0/3 checkpoints
PendingUpcoming
29 Oct → 30 Oct
0%
Painting
Girder Painting
Shot blasting (SA 2.5)Production
Deepak Kumar · 0/2 checkpoints
PendingUpcoming
01 Nov → 02 Nov
0%
Primer + intermediate + finish coatsProduction
Deepak Kumar · 0/3 checkpoints
PendingUpcoming
03 Nov → 06 Nov
0%
DFT checkQuality Check
Deepak Kumar, Pooja Nair · 0/2 checkpoints
PendingUpcoming
07 Nov → 07 Nov
0%
Dispatch
Dispatch Package
Dispatch documentsDocumentation
Ramesh Gupta · 0/4 checkpoints
PendingUpcoming
06 Nov → 07 Nov
0%
Packing & loadingProduction
Ramesh Gupta · 0/4 checkpoints
PendingUpcoming
08 Nov → 09 Nov
0%