Masters
Configure work types, task labels, components with task presets, and roles.
8 components · 23 preset tasks
Fabrication
2 tasks · 6 checkpoints
- 1.End carriage fabricationProductionstarts day 3 · 5 days
- Cutting
- Fit-up
- Welding
- Stress relieving
- 2.Dimensional checkQuality Checkstarts day 8 · 1 day
- Wheel base check
- Diagonal check
5 tasks · 16 checkpoints
- 1.Plate & section procurementProcurementstarts day 0 · 4 days
- PO released
- Plates received
- MTC verified
- 2.Cutting plan & nestingPlanningstarts day 2 · 2 days
- Nesting drawing approved
- Plates marked
- 3.Cutting & web/flange prepProductionstarts day 4 · 3 days
- Flange plates cut
- Web plates cut
- Diaphragms cut
- Edge bevelling
- 4.Girder fit-up & weldingAssemblystarts day 7 · 6 days
- Diaphragm fit-up
- Box closing
- Longitudinal welding
- Camber check
- 5.Weld inspection (DPT/UT)Quality Checkstarts day 13 · 2 days
- Visual inspection
- DPT
- UT report
Machining
2 tasks · 5 checkpoints
- 1.Drum groovingProductionstarts day 6 · 4 days
- Facing
- Rope grooving
- Flange boring
- 2.Groove profile inspectionQuality Checkstarts day 10 · 1 day
- Pitch check
- Groove radius check
4 tasks · 11 checkpoints
- 1.Forged wheel blanksProcurementstarts day 0 · 5 days
- PO released
- Blanks received
- 2.Wheel turning & boringProductionstarts day 5 · 4 days
- Rough turning
- Boring
- Finish turning
- Keyway
- 3.Shaft machiningProductionstarts day 5 · 3 days
- Turning
- Keyway milling
- Grinding
- 4.Wheel & bearing assemblyAssemblystarts day 9 · 2 days
- Bearing fitting
- Run-out check
Electrical
4 tasks · 11 checkpoints
- 1.Panel GA & wiring drawingDrawing / Designstarts day 0 · 3 days
- GA approved
- Wiring diagram approved
- 2.Switchgear & VFD procurementProcurementstarts day 2 · 6 days
- VFDs received
- Contactors & MCBs received
- Cables received
- 3.Panel wiringAssemblystarts day 8 · 4 days
- Power wiring
- Control wiring
- Ferruling & dressing
- 4.Panel testingTestingstarts day 12 · 2 days
- IR test
- Function test
- VFD parameter setting
1 tasks · 3 checkpoints
- 1.Festoon cabling & trolleysAssemblystarts day 9 · 3 days
- Cable cutting
- Trolley assembly
- Termination
Painting
3 tasks · 7 checkpoints
- 1.Shot blasting (SA 2.5)Productionstarts day 15 · 2 days
- Blasting
- Surface profile check
- 2.Primer + intermediate + finish coatsProductionstarts day 17 · 4 days
- Primer coat
- Intermediate coat
- Finish coat
- 3.DFT checkQuality Checkstarts day 21 · 1 day
- DFT readings recorded
- Touch-up
Dispatch
2 tasks · 8 checkpoints
- 1.Dispatch documentsDocumentationstarts day 20 · 2 days
- Packing list
- Invoice & e-way bill
- Test certificates
- Manuals
- 2.Packing & loadingProductionstarts day 22 · 2 days
- Match marking
- Packing
- Trailer loading
- Gate pass