PTProTaskProduction tracker

Masters

Configure work types, task labels, components with task presets, and roles.

8 components · 23 preset tasks

Fabrication

2 tasks · 6 checkpoints
  1. 1.
    End carriage fabricationProductionstarts day 3 · 5 days
    • Cutting
    • Fit-up
    • Welding
    • Stress relieving
  2. 2.
    Dimensional checkQuality Checkstarts day 8 · 1 day
    • Wheel base check
    • Diagonal check
5 tasks · 16 checkpoints
  1. 1.
    Plate & section procurementProcurementstarts day 0 · 4 days
    • PO released
    • Plates received
    • MTC verified
  2. 2.
    Cutting plan & nestingPlanningstarts day 2 · 2 days
    • Nesting drawing approved
    • Plates marked
  3. 3.
    Cutting & web/flange prepProductionstarts day 4 · 3 days
    • Flange plates cut
    • Web plates cut
    • Diaphragms cut
    • Edge bevelling
  4. 4.
    Girder fit-up & weldingAssemblystarts day 7 · 6 days
    • Diaphragm fit-up
    • Box closing
    • Longitudinal welding
    • Camber check
  5. 5.
    Weld inspection (DPT/UT)Quality Checkstarts day 13 · 2 days
    • Visual inspection
    • DPT
    • UT report

Machining

2 tasks · 5 checkpoints
  1. 1.
    Drum groovingProductionstarts day 6 · 4 days
    • Facing
    • Rope grooving
    • Flange boring
  2. 2.
    Groove profile inspectionQuality Checkstarts day 10 · 1 day
    • Pitch check
    • Groove radius check
4 tasks · 11 checkpoints
  1. 1.
    Forged wheel blanksProcurementstarts day 0 · 5 days
    • PO released
    • Blanks received
  2. 2.
    Wheel turning & boringProductionstarts day 5 · 4 days
    • Rough turning
    • Boring
    • Finish turning
    • Keyway
  3. 3.
    Shaft machiningProductionstarts day 5 · 3 days
    • Turning
    • Keyway milling
    • Grinding
  4. 4.
    Wheel & bearing assemblyAssemblystarts day 9 · 2 days
    • Bearing fitting
    • Run-out check

Electrical

4 tasks · 11 checkpoints
  1. 1.
    Panel GA & wiring drawingDrawing / Designstarts day 0 · 3 days
    • GA approved
    • Wiring diagram approved
  2. 2.
    Switchgear & VFD procurementProcurementstarts day 2 · 6 days
    • VFDs received
    • Contactors & MCBs received
    • Cables received
  3. 3.
    Panel wiringAssemblystarts day 8 · 4 days
    • Power wiring
    • Control wiring
    • Ferruling & dressing
  4. 4.
    Panel testingTestingstarts day 12 · 2 days
    • IR test
    • Function test
    • VFD parameter setting
1 tasks · 3 checkpoints
  1. 1.
    Festoon cabling & trolleysAssemblystarts day 9 · 3 days
    • Cable cutting
    • Trolley assembly
    • Termination

Painting

3 tasks · 7 checkpoints
  1. 1.
    Shot blasting (SA 2.5)Productionstarts day 15 · 2 days
    • Blasting
    • Surface profile check
  2. 2.
    Primer + intermediate + finish coatsProductionstarts day 17 · 4 days
    • Primer coat
    • Intermediate coat
    • Finish coat
  3. 3.
    DFT checkQuality Checkstarts day 21 · 1 day
    • DFT readings recorded
    • Touch-up

Dispatch

2 tasks · 8 checkpoints
  1. 1.
    Dispatch documentsDocumentationstarts day 20 · 2 days
    • Packing list
    • Invoice & e-way bill
    • Test certificates
    • Manuals
  2. 2.
    Packing & loadingProductionstarts day 22 · 2 days
    • Match marking
    • Packing
    • Trailer loading
    • Gate pass